Thanks to God, 2017 begins with much construction and a stable church congregation growing in faith. At the beginning of the year workers initiate the land movement and infrastructure work. Fewer and fewer items remain to open a clinic of excellence that will serve many needy in the name of Christ. We trust in God for great blessings this year, that he will glorify his name mightily in this project and heal many.

Monthly Progress 2017

January

  1. Construction begins on land movement, septic system, site drainage system.
  2. Construction continues with concrete drives, patio.
  3. Local private school holds graduation ceremony in MCI building.
  4. Higueronal church holds night vigil and worship to start the new year.
  5. Higueronal church continues Thursday and Sunday meetings, with January Sunday average attendance 43.

February

  1. Construction continues on land movement, septic and water systems, site drainage.
  2. Higueronal church continues Thursday and Sunday meetings, with February Sunday average attendance 32. Attendance decreased in February with bus under repair.

March

  1. Construction continues on land movement, septic and water systems, lake reservoir, site drainage, internal road, parking lots.
  2. Higueronal church continues Thursday and Sunday meetings, with March Sunday average attendance 36. Attendance remains decreased with bus under repair.

April

  1. Construction continues on land movement, septic and water systems, lake reservoir, site drainage, internal road, parking lots.
  2. Higueronal church continues Thursday and Sunday meetings, with April Sunday average attendance 30. Attendance remains decreased with bus under repair.

May

  1. Construction continues on land movement, septic and water systems, lake reservoir, site drainage, internal road, parking lots. 
  2. Higueronal church continues Thursday and Sunday meetings, with May Sunday average attendance 32. Attendance remains decreased with bus under repair.
  3. Visiting minister Luis Pinto from Venezuela begins six-month evangelism work with the congregation.

June

  1. Construction continues on site drainage, land movement, septic and water tanks. 
  2. Higueronal church continues Thursday and Sunday meetings, with some Thursday meetings in member homes.  June Sunday average attendance 32.  Attendance remains decreased with bus under repair.
  3. The church held an event for fathers. 
  4. Visiting minister Luis Pinto from Venezuela continues work with the congregation.

July

  1. Construction continues on site drainage.
  2. Workers advance various outdoor maintenance projects and landscaping.
  3. Construction main focus changed indoors due to rainy season. Workers advance clinic wing ceiling, floors.
  4. Higueronal church continues Thursday and Sunday meetings, with Thursday meetings in member homes. July Sunday average attendance 26. Attendance remains decreased with bus under repair.
  5. The church held a midnight service attended by visitors.
  6. Visiting minister Luis Pinto from Venezuela continues work with the congregation.

August

  1. Construction continues on clinic rooms finish work.
  2. Construction continues with outdoor maintenance projects.
  3. Higueronal church continues Sunday meetings. Thursday meetings are suspended during August. August Sunday average attendance 26. Attendance remains decreased with bus under repair.
  4. Visiting minister Luis Pinto from Venezuela returns to his family in Venezuela due to unrest in that country. The congregation holds a luncheon to thank him for his work.

September

  1. Construction continues on clinic rooms finish work.
  2. Construction continues with outdoor maintenance projects, including container remodel.
  3. Construction initiated on clinic restaurant.
  4. Higueronal church continues Sunday meetings and resumed Thursday meetings. September Sunday average attendance 31.